ACN 109 200 900
AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT 18 July 2016 EDENCRETETM - US UPDATE MARTA Brady Mobility Facility Project Test Results HIGHLIGHTS Test results from two separate independent laboratories of the concrete used in the MARTA Brady Mobility Facility Trial in May 2016 showed EdenCreteTM produced the following improvements: First Laboratory:
| 38% |
| 59% |
| 24% |
| 47% |
- Compressive Strength Increase - 25% Second Laboratory:
- Shrinkage Reduction (Improvement) - 9%
Level 15, 197 St Georges Terrace, Perth, Western Australia 6000 Telephone: (08) 9282 5889 Facsimile: (08) 9282 5866
Email: mailroom@edenenergy.com.au
DETAILS Eden Energy ("Eden") (ASX: EDE) is pleased to announce that it has now received the test results from two independent laboratories of its first commercial government infrastructure project. These tests, taken after the concrete test cylinders had cured for 28 days, produced further very encouraging results. The project was undertaken in May 2016 (see Eden announcement ASX: EDE 16 May 2016) at the Metropolitan Atlanta Rapid Transit Authority (MARTA) Brady Mobility Facility in Atlanta, Georgia (see Figures 1 and 2 below).A section of a new concrete hardstand area was installed using EdenCreteTM enriched concrete at a new state-of-the-art bus garage that is being constructed to replace the existing garage at the MARTA Brady Mobility facility in Atlanta, Georgia.
The dosage rate used for the trial of 3 gallons of EdenCreteTM per cubic yard of concrete, was lower than the 4 gallons per cubic yard that had originally been planned, due to the increased volume of concrete that was finally required.
However, based on other trials, the EdenCreteTM had still been assumed would at least double the service life of the concrete by enhancing the concrete's performance characteristics.
The results produced from these tests are considered to support this assumption.
Figure 1. Brady Mobility Facility with EdenCreteTM slab site being prepared (shown in upper left)
Figure 2. EdenCreteTM enriched slab being installed
As previously announced, two independent test laboratories in Georgia each took test samples of both the standard concrete and the EdenCreteTM enriched concrete. The results reported from each of the two laboratories are shown in Figures 3 and 4 below.
ATC Laboratory ResultsIdentification | Pour Date | Test Age (Days) | Compressive Strength (lbs./in.2) | % Improvement by | ||||
Sample 1 | Sample 2 | Sample 3 | Average | |||||
EdenCrete Truck 1 | 5/12/2016 | 28 | 9510 | 9610 | 9360 | 9493 | ||
EdenCrete Truck 2 | 5/12/2016 | 28 | 8210 | 8480 | 8370 | 8353 | ||
EdenCrete Truck 1 | EdenCrete Truck 2 | |||||||
MARTA Reference Truck 1 | 5/14/2016 | 28 | 8010 | 7850 | 7890 | 7917 | 20% | 6% |
MARTA Reference Truck 2 | 5/14/2016 | 28 | 6480 | 6670 | 6290 | 6480 | 47% | 29% |
MARTA Reference Truck 3 | 5/14/2016 | 28 | 7020 | 6670 | 6750 | 6813 | 39% | 23% |
MARTA Reference Truck 4 | 5/14/2016 | 28 | 6890 | 6790 | 6940 | 6873 | 38% | 22% |
MARTA Reference Truck 5 | 5/14/2016 | 28 | 7630 | 7730 | 7510 | 7623 | 25% | 10% |
Avg. of ALL Marta Reference Trucks | 7141 | |||||||
Avg. of ALL EdenCrete Trucks | 8923 | 25% overall improvement |
Figure 3 ATC Laboratory Test Results -MARTA Brady Mobility
TEC Normalised Laboratory Results *Property | Test Procedure | Reference | EdenCrete | % Improvement by EdenCrete |
Air Content (%) | ASTM C231 | 6.1 | 4.0 | |
Slump (in.) | ASTM C 143 | 7.25 | 7.25 | |
Concrete Temperature (oF) | ASTM C1064 | 84 | 82 | |
Unit Weight (lbs./ft.3) | ASTM C138 | 140.8 | 145.1 | |
Compressive Strength | ASTM C39 | 6160 | 8490 | 38% |
Split-Tensile Strength | ASTM C496 | 255 | 405 | 59% |
Modulus of Elasticity | ASTM C469 | 3161600 | 3933767 | 24% |
Abrasion Resistance | ASTM C944 | 0.17 | 0.08 | 47% |
Length Change | ASTM C157 | 0.048 | 0.044 | 9% |
Note: Freeze/Thaw and Permeability testing in-progress |
Figure 4 TEC Laboratory Test Results -MARTA Brady Mobility
The state of the art mobility facility** will house the administrative functions, operations, and maintenance facilities for a fleet of up to 200 Mobility vehicles (specialized vans and cutaway buses). The EdenCreteTM section will be subjected to extreme rolling frictional forces due to the constant wear and abuse of large vehicle tyres when turning on the slab from day to day, and will be evaluated over time relative to the rest of the concrete not containing EdenCreteTM.
The targeted extension of concrete service life is intended to ultimately reduce the in-service cost for the project by significantly deferring disruptive and costly repair projects due to excessive cracking and/or abrasion over time.
MARTAMARTA has served the Atlanta metropolitan area for more than 35 years. It operates a number of sustainability programs that are applied to many areas within the organization including its fleet of compressed natural gas (CNG) buses. MARTA's Laredo Bus Garage has the largest solar canopy installation in the state of Georgia, and the second largest structure of its kind at a U.S. transit system.
SummaryWhilst this first infrastructure contract was only for a small demonstration project, the results of these laboratory tests have greatly increased the probability that the longer term performance of the EdenCreteTM section of the concrete slab will reproduce similar positive results to those achieved in earlier trials focusing on similar performance characteristics, resulting in a further significant milestone for Eden in its ongoing efforts for EdenCreteTM to penetrate and become accepted for use in the huge U.S. infrastructure market.
* Due to the 2.1% reduction in air content (which increases the strength) in the EdenCreteTM concrete, the compressive strength results have been normalised in accordance with conservative industry standards by adding 500 psi per 1% difference in air content (i.e. adding 1050 psi) to the results for the control cylinders.
** http://maintenancedesigngroup.com/projects/marta-brady-mobility-facility/
Eden Energy Limited published this content on 18 July 2016 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 17 July 2016 22:58:09 UTC.
Original documenthttp://www.edenenergy.com.au/pdfs/245b167afd66ffe8a6185fba02989818.pdf
Public permalinkhttp://www.publicnow.com/view/14B2E5D89D531DDBCEC28979615263D8B69A0E01